Laserfiche WebLink
Attachment 4 <br /> Compliance . <br /> Task Specific Action per Order Date <br /> 5. Relocation of access roads to preclude transport <br /> over caps covering the Group 1 disposal trenches. <br /> 7. Control of surface drainage to prevent ponding, <br /> contact with waste materials, and overflow of <br /> containment structures. <br /> 8. Regrading of cover on Group 2 disposal area to <br /> prevent ponding of surface water. <br /> Commence construction 13 June 1983 <br /> Construction time l0 days <br /> Finish construction 24 June 1983 <br /> Submittal of compliance report 15 Jul 1983. <br /> 6. Relocation and proper disposal of drilling mud <br /> wastes and wastes received from FMC, Modesto <br /> that are improperly located on caps covering <br /> Group 1 disposal trenches and Group 2 waste <br /> areas. <br /> Commence construction 30 May 1983 <br /> Construction time 10 days <br /> Finish construction 10 June 1983 <br /> Submittal of compliance report 15 Jul 1983 <br />