Laserfiche WebLink
October 11,2017 <br /> Page 2 of 5 <br /> Reference: Remediation Well Destruction Work Plan <br /> 3.0 Proposed Scope of Work <br /> STTC is proposing to remove forty-eight(48)wells from the Site.The scope of work will include the following: <br /> • Obtain all necessary permits from SJCEHD; <br /> • Provide a site-specific health and safety plan; <br /> • Perform utility clearance of areas surrounding wells to be destroyed; <br /> • Air-knife or hand core around each well to be destroyed;and, <br /> • Destroy all ozone wells(designated"OS"on the attached Figure 2)by overdrillingl and grouting to <br /> the surface per SJCEHD requirements. <br /> A summary of the planned field work is presented below. Field and laboratory procedures are provided in <br /> Attachment 1. <br /> 3.1 HEALTH AND SAFETY PLAN <br /> Stantec will provide a site-specific Health and Safety Plan(HASP)for the above scope of work as required by <br /> the Occupational Health and Safety Administration(OSHA)standard guidelines(29 CFR 1910.120),and by <br /> California Occupational Health and Safety Administration (Cal-OSHA) guidelines (CCR Title 8, Section <br /> 5192). Prior to the commencement of fieldwork,the HASP will be updated with appropriate field personnel <br /> and subcontractor information. Subcontractors working at the Site will also maintain their own HASP that <br /> covers the specific activities they are completing, and will be reviewed by Stantec prior to initiating field <br /> activities.The field staff and contractors will review and sign the HASPs before beginning field operations at <br /> the Site,and at a minimum daily during field operations. <br /> 3.2 PERMITTING <br /> Well destruction permits will be obtained from SJCEHD prior to the commencement of field activities. No <br /> other agency permitting is anticipated for completion of the proposed work. <br /> 3.3 BOREHOLE CLEARANCE ACTIVITIES <br /> Stantec will mark the proposed locations with white paint, as required by law, and contact Underground <br /> Service Alert(USA)at least one day before a 48-hour review period,prior to the start of boring activities to <br /> notify all utility operators in the area to clear the marked locations. Additionally, a private utility location <br /> 1 For wells where overdilling is unachievable due to structures,utilities,etc.that have been constructed after the remediation wells were <br /> installed,such that a limited access drill rig cannot safely complete the work,those affected wells will be properly destroyed by pressure <br /> grouting methods. <br /> Design with community in mind <br />