Page 10 of 13 <br />3. When piping is placed on the bed, proceed to "First Test" (below) prior to <br />backfilling trenches. <br />6-150.12 TESTING OF PIPING <br />A. Notify the Owner's Representative, who MUST observe all tests, at least 24 hours in <br />advance of any tests. <br />B. The Contractor 'is responsible for all labor, material, and equipment to conduct <br />pressure tests (air or hyrdostatic) of all product, vent and vapor recovery piping. <br />C. FIRST TEST (Prior To Backfilling Pipe Trenches): Do not connect piping to tanks, <br />remote pumps or dispensers. <br />1. The entire piping system, i.e., product, vent and vapor recovery (where <br />applicable), shall be tested in accordance with the following three step <br />procedure. <br />2. <br />a. <br />b. <br />Step One: Install pressure application system that includes two pressure <br />gauges (15 psig maxim m). Apply 10 prig pressure to each piping system. <br />Soap all joints using approved soap solution. Carefully observe each joi <br />for evidence of leaks. <br />Step Two: Protect area around piping systems to be tested to prevent <br />workmen, passers-by, etc., from entry. Install pressure application sy <br />that includes two pressure gauges (150 psig maximzn). Apply 60-75 psig <br />pressure to each piping system, hold for 30 minutes, release pressure. <br />C. CAUITON: Be sure to disconnect at tank or suhmerged pump before applying <br />arm. <br />d. <br />.7•• � �. :1.11 • •1 «� • � . • • � ... II.?. •.. / • ;• � <br />17� <br />•• ••• •• til:+mulzin <br />e. <br />Step Three: Protect area ara-4 piping systems to be tested to prevent <br />workmen, passers-by, etc., from entry. Install pressure application system <br />that includes two pressure gauges (10 psig maximum). Apply 5 psig pressure <br />to each piping system, hold for 30 minutes, release pressure. <br />CONTRACIOR SHATL AFdW1GE AND PAY FOR THE PERFORMANCE OF A S= CE= = <br />PRECISION TEST (PFrRO-=, HUNTER OR NDE TECH.) OF 111E =IRE SYSTEM PRIOR <br />COVERING TAI AND P!RO;XJCT PIPING. TEST S11AM BE CONDUCTED USING WMETI OR <br />PRODUCT. NOTIFY01 HOURS IN ADVANCE OF E1 CanRACTOR Is READy• - <br />a. <br />6-151 ELE=CAL WORK <br />6.21 <br />