Laserfiche WebLink
Schedule Name: MARLEY COOLING TOWER COMPANY <br /> Project Manager: D.W. BATES ` <br /> As of date: 17-Apr-87 11:15am Schedule File: B:SCH2-23 <br /> OVERALL SCHEDULE FOR CLEAN UP AT STOCKTON PLANT(REVISED APR 08,1987) <br /> 87 88 <br /> Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct <br /> Who Status 2 2 1 1 1 1 3 1 1 2 1 4 1 1 1 2 1 1 1 1 3 <br /> HYDROGEOLOGIC ASSESSMENT RPT. +++++++++++++ . <br /> IGENERAL CONSTRUCTION C +++++++++++++++++++++++ <br /> F1STARTUP TREATMENT PLANT C M <br /> IOPERATIONAL TEST. - _ - -- ___ C.. - ( . === <br /> 1TREATMENT PLANT OPERATIONAL C M <br /> 2INT POND CLOSURE PLAN DEVELO. C +++++++ <br /> 2INT POND CLOSURE PLAN REVIEW C <br /> 2INT POND CLOSURE PLAN APPROVL M ' <br /> 2POND LIQUID REMOVAL 0 <br /> 2POND BOTTOM SAMPLING C ' <br /> 2SLUDGE MANAGEMENT CONTRACT C _ <br /> L 2SLUDGE MANAGEMENT <br /> k3" - 2INT CAP CONTRACT C <br /> Ifa 2INT CAP INSTALLATION C <br /> 2INT POND CERTIFICATION INSPT. C <br /> 2INT POND CLOSURE COMPLETE M <br /> '• 3NPDES PERMIT MODIFICATIONS D M <br /> 3NPDES PERMIT REVIEW AND APPRO +++++++++.++++ <br /> � 3PHASE III WELL INSTALLATION D M. <br /> 3PHASE III REPORT PREPARATION C +++++++++++++++++++ --- - -- <br /> _�_- 3PHASE III REPORT REVIE4 <br /> 3TEMP EXTRACTION WELL INSTAL. <br /> 3TEMP GRND WATER MAIN DESIGN C <br /> 3TEMP GRND WATER MAIN INSTAL. C • I ___ ' <br /> 3EXTRATRCTION WELL TESTING C <br /> ,I 3GROUND WATER OPERATION COMMEN M. <br /> 4WORK PLAN UPDATE C •+++++ - ._ <br /> 4WORK-PLAN-APPROVAL - ) __________ <br /> x'I 4POND BOTTOM SAMPLE EVALUATION C =______=_• <br /> si 4SOUTH YARD DITCH SAMPLING .++++++++.+++ +++ <br /> 4SOUTH YARD RUN-OFF SAMPLE _ <br /> e --_4SOILS ASSESSMENT REPORT PREP C I -� __ _______________ -"" -- <br /> 4SOILS ASSESSMENT REPORT REVIE C <br /> 4ASSESS. PROGRAM REPORTS APPRO C M=_===___ <br /> 4FINAL MITIGATION PLAN PREPAR C <br /> ----"IF-IGATION PLAN REVIEW C <br /> 4MITI 'ATION PLAN APPROVED C 1 .M <br /> 4START MITIGATION PLAN - C_ I . <br /> :.I """` _ <br /> D Done === Task - Slack time (==---), or <br /> .•I C Critical +++ Started task Resource delay (-----) <br /> R Resource conflict M Milestone > Conflict <br /> -- ----p"Partial dependency <br /> Scale: Each character equals 1 week ___________________________________________________ <br /> fl <br /> �! - - TIME LIN€ Gantt Chart Report - Strip 1 - ------- <br /> �.fl <br /> al <br /> x <br /> x <br /> 6 <br />