TABLE 1 . MCTC SOIL FLUSHING SCHEDULE <br /> ;; <br /> DATE EVENT <br /> September 16, 1991 Start confirmation drilling; neutron <br /> probe consultant completes final <br /> suite of measurements. <br /> September 20, 1991 Complete drilling and submit samples <br /> to laboratory. <br /> October 4, 1991 Final soil physical data received from <br /> laboratory. <br /> October 8, 1991 Neutron probe consultant receives <br /> soil data. <br /> October 21, 1991 Neutron probe consultant submits final <br /> report. B&V begins final pilot study <br /> evaluation and full scale design <br /> modifications. <br /> November 4, 1991 Tentative quarterly ground water <br /> and lysimeter sampling, data to <br /> be included in pilot study evaluation. <br /> November 26, 1991 S&V submits pilot study evaluation and <br /> full scale design to MCTC and regulatory <br /> agencies. Regulatory comment period <br /> begins. <br /> December 30, 1991 Regulatory comment period closed. B&V <br /> addresses comments. <br /> January 17, 1992 S&V resubmits full scale design. <br /> February 17, 1992 Construction of the full scale system <br /> begins. <br /> April 6, 1992 Full scale system operational. <br /> April 20, 1992 Turn on full scale system. <br /> MCTC SOIL FLUSHING <br /> 8&V Project N 11854.882 <br /> CAW25G:SFSCHED.WK1 <br /> 08/28191 <br />