Attachment 2 <br /> Schedule for Ground Water Collection System <br /> This memorandum describes the current schedule for the ground water collection <br /> system at the Marley Cooling Tower Company (MCTC) facility in Stockton, <br /> California. <br /> The installation of the ground water collection piping and system control conduit has <br /> been completed in the residential areas. Activities yet to be completed in the <br /> residential areas include installation of the pumping station, well vaults, and control <br /> cabinets. The ground water force main in the North and South Yards is currently <br /> being constructed. Completion of all activities is scheduled for October 15, 1991. <br /> System inspection and checkout is scheduled for the week of October 21, 1991. Full- <br /> scale startup will be coordinated with the completion of the water treatment plant <br /> expansion activities tentatively scheduled for December 4, 1991. See Table 2 for a <br /> detailed schedule of activities. <br />