i , <br /> Del Monte AS/cat Cost Est <br /> i. <br /> Del Monte Plant 33 <br /> Air Stripper and Offgas Control (catalytic oxidation) <br /> SF031604.DA <br /> QTY Unit $/unit COST COMMENT <br /> 1 SITEWORK <br /> µ Site Preparation 1 LS 5,000 5,000 Allowance <br /> EQUIPMENT <br /> LL Flow EQ Tank 1 LS $6,000 $6,000 3,000 gal tank <br /> Influent Pumps 4 each $1,500 $6,000 <br /> Air Stripping System 2 each $15,000 $30,000 <br /> Acid Addition System 1 LS $4,000 $4,000 <br /> Caustic Add. System 1 LS $4,000 $4,000 <br /> Blowers 2 each $2,000 $4,000 <br /> Effluent Pumps 2 each $1,500 $3,000 <br /> Catalytic Ox Unit 1 LS $65,000 $65,000 <br /> K--------tea <br /> Subtotal a 127,000 <br /> Unquantified Items (5% of subtotal) 6,350 <br /> Freight Allowance (10% of subtotal) 12,700 <br /> Installation Allowance (15% of subtotal) 19,050 i <br /> Subtotal 165,100 . <br /> i <br /> Y e - <br /> i MECHVVICAL ( 15% of Equipment Total ) 24,765 <br /> m: ELECTRICAL ISC { 15% of Equipment Total ) 24,765 <br /> ----------- <br /> s CONSTRUCTION COST SUBTOTAL 214,630 <br /> Contingency ( 25% of CCS ) 53,658 i <br /> -R-s------- . <br /> TOTAL CONSTRUCTION COST 268,288 t <br /> Mob,Demob,Bonding, 6 Insurance ( 8% of TCC ) 21,463 i <br /> Permitting s Legal ( 5% of TCC ) 13,414 <br /> S Services During Construction ( 5% of TCC ) 13,419 <br /> Start-Up Costs ( 5% of TCC ) 13,414 ! <br /> ----------- <br /> T. TOTAL IMPLEMENTATION COST 329,993 r <br /> r Engineering Design Costs { 12% of TIC ) 39,599 <br /> TOTAL CAPITAL COST 370,000 <br /> 4 <br /> Page 1 <br /> t. <br /> k ; <br />