Work Plan to Install <br /> Additional Monitoring <br /> ARCADIS Wells <br /> Former OCC Lathrop Facility <br /> PW21, PW25, and PW30). Each borehole will be advanced by a C-57 licensed drilling <br /> contractor using mud rotary drilling methodology(unless an alternative method is <br /> deemed more appropriate) under the supervision of ARCADIS staff working under the <br /> direction of an ARCADIS Professional Geologist.The drill rig will be equipped with a <br /> minimum 12-inch-diameter drill bit for the proposed 2-inch nested wells or minimum 8- <br /> inch-diameter drill bit for the proposed single 2-inch wells. Borings will be continuously <br /> logged,and the lithology encountered will be recorded using the Unified Soil <br /> Classification System by an ARCADIS field geologist.After each boring has been <br /> advanced to its proposed total depth,wells will be constructed using a five foot long 2- <br /> inch-diameter PVC sump, 0.020 slot PVC screen, and blank Schedule 80 PVC casing. <br /> In addition, centralizers will be placed above and below the screen and in 50 foot <br /> intervals above the screen. <br /> 3.2.3 Filter Pack Installation and Grouting <br /> After the screen and blank casing have been placed inside the open borehole,the well <br /> annulus materials will be added by pumping the materials through a tremie pipe.The <br /> well annulus in the screened intervals will be filled with number 3 sand to a minimum of <br /> 2 feet above the screen.A minimum of 3 feet of bentonite chips will be placed and <br /> hydrated above the sand pack to isolate the screened interval and to prevent the <br /> entrance of grout into the sand pack. In boreholes containing a nested pair of wells, the <br /> annulus from 2 feet above the deeper screen to 5 feet below the shallower screen will <br /> be filled with bentonite.Typical proposed single and nested well construction details <br /> are presented on Figures 3 and 4, respectively. <br /> After the bentonite seal has hydrated, neat cement grout will be placed in the annular <br /> space above the bentonite seal to the ground surface to seal the remainder of the <br /> borehole. The SJCEHD will be notified before the wells are sealed so that a field <br /> inspector can witness this activity. <br /> 3.2.4 Well Development <br /> Grout will be allowed to cure for a minimum of 48 hours before development activities <br /> are conducted. Each well will be developed using one or more of the following <br /> methods: air development,water jetting, and mechanical surging.The specific <br /> methods and duration of well development will be determined in the field based on <br /> professional judgment. Water quality parameters, including pH, conductivity, and <br /> turbidity,will be monitored to track and document progress during development. <br /> 2014.03.13 mw installation work plan_fnal.doc 3 <br />