L' <br />Vector Engineering <br />Daily Field Report <br />Job Number: 031602.00 <br />Project Name: <br />Client Or Manager. Daily Field Report Sequence Number Days left in contract <br />Construction of 2 Landfill Modules- <br />County of San Joaquin 21 59 <br />Foothill Landfill <br />Location of Work: <br />Owner's Or Client's Representative <br />Date: <br />Day of The Week: <br />Stockton Ca. <br />Mike Carroll <br />7-17-03 <br />Thursda <br />General Contractor. <br />Liner Contractor: <br />Project Engineer: <br />Reviewed By: <br />Wood Brothers <br />D&E Construction <br />Bryan Fritzler <br />General Foreman: <br />Liner Superintendent: <br />Other. <br />Tony Peichoto / Mario Garza <br />Eric Downs <br />Source and Description of Fill Material: <br />Weather. <br />CQA Technician: <br />On site tan Brown sandy silt <br />Clear Warm 980 <br />Frank Dell -Era / Jeremy Freas <br />Equipment Utilized: <br />3-631C Cat Scraper, D9G Dozer, D6 Cat Dozer with disc, D5CXL Cat Dozer, Case Tractor with laser scraper box, 825 Sheepsfoot <br />Cat compactor, 3 -Water Trucks, Drill Rig, 140 Cat Grader.. <br />NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 11 Man crew Krazan/Soil Probe: 3 Man crew <br />Wood Bros. continued to place, moisture condition and compact foundation layer material on the northern <br />and Middle portion of Module 1. Wood Bros. hauled material from soil borrow area A to the 4`h , 5th and 6th <br />bays off the northern slope for the 1St lift utilizing the D9 dozer and 2-631 scrapers. Wood brothers continued <br />to utilize 2- water trucks, the D6 with disc and the tractor with scraper box to moisture condition the <br />foundation layer material prior to compaction. Wood bros. continued to utilize the 825 to compact the lower <br />portion with the scrapers wheel rolling the surface. Wood bros. had the D5CXL dozer, water truck and <br />Grader moisture conditioning and processing the soil material on the slopes. <br />*Krazan/Soil Probe drilled wells #3-#4-#5-#7-#10. Krazan completed drilling well #10. Krazan only drilled <br />no placement of probes or backfill occurred. Krazan brought in a skip loader to clean spoils and remove any <br />dry grass from the drilling areas. Krazan had a load of 3/8 pea gravel delivered from Granites Tracy plant for <br />construction of the soil gas wells. Mark Edwards turned in drill logs to CQA. <br />Vector Engineering, Inc. CQA observed placement and tested compaction of foundation layer material <br />placed on the northern floor of Module 1. CQA performed several density tests with all tests meeting the <br />required specifications for this project in the 3`d bay 2nd lift, all tests performed in the 4th bay lst lift failed <br />either moisture or compactive effort. Wood Bros. will rework the entire 4th bay. <br />Vector discussed with Wood bros. CQA explained to Tony and Mario that the material from the borrow area is not processed as good as the floor <br />material. The material is inconsistent as far as breaking up of the clods and there are large chunks, which are out of specification. Wood Bros. <br />will need to recompact the entire 5`h bay. Krazan will drill gas wells but not install anything until the county inspector is on site tomorrow. The <br />county representative had Krazan bring in another type of pea gravel from Granite in Tracy. <br />41 <br />File Name: Foothill Landfill Prepared By: Frank Dell -Era Reviewed By: <br />