Vector Engineering <br />Daily Field Report <br />Job Number: 031602.00 <br />Project Name: <br />Client Or Manager. <br />Daily Field Report Sequence Number. Days left in contract <br />Construction of 2 Landfill Modules- <br />County of San Joaquin <br />27 53 <br />Foothill Landfill <br />Location of Work: <br />Owner's Or Client's Representative <br />Date: <br />Day of The Week: <br />Stockton Ca. <br />Mike Carroll <br />7-25-03 <br />F ida <br />General Contractor. <br />Liner Contractor. <br />Project Engineer. <br />Reviewed By: <br />Wood Brothers <br />D&E Construction <br />Bryan Fritzler <br />General Foreman: <br />Liner Superintendent: <br />Other. <br />Tony Peichoto / Mario Garza <br />Eric Downs <br />Source and Description of Fill Material: <br />Weather. <br />CQA Technician: <br />On site Brown sandy silt <br />Clear Warm 950 <br />Frank Dell -Era / Jeremy Freas <br />tqurpment uunzed: <br />2-631C Cat Scraper, D9G Dozer, D6 Cat Dozer with disc, Case Tractor with laser scraper box, 825 Sheepsfoot Cat compactor, 2 - <br />Water Trucks. <br />NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 10 Man crew D&E: 2 Man crew <br />Wood Bros. continued to place, moisture condition and compact foundation layer material on the southern <br />portion of Module 1. Wood Bros. processed and compacted the 8" and 91h bay 2nd lift utilizing the D6 with <br />disc, 825 sheepsfoot compactor, case tractor with scraper box and 2 -water trucks. Wood Bros started <br />processing material for a thin lift in the 6th bay where they were a little below tolerances. Wood Bros. had the <br />scrapers wheel rolling areas moisture conditioned to seal. <br />D&E construction utilized the TH83 forklift to unload 2 load of GCL totaling approximately 79,050ft2. <br />OVector Engineering, Inc. CQA observed placement and tested compaction of foundation layer material. <br />CQA performed several density tests with all tests meeting the required specifications. CQA observed <br />unloading and logged all liner materials delivered to the site. CQA ran a sieve, moisture density relation ship <br />curve on the slope materials. <br />Vector discussed with Wood bros. they will complete the southern portion foundation layer then work on the V ditches. <br />0 <br />File Name: Foothill Landfill Prepared By: Frank Dell -Era Reviewed By: <br />