LFG CONTROL CORPORATION <br />11 <br />REPORT NO: 3 <br />DATE: 5/28/2009 <br />WEATHER: Pt. Cloudy / Hot <br />PROJECT: Forward Landfill 2009 Gas System Improvements <br />CLIENT: Allied Waste <br />CONTRACTOR: American Environmental Group <br />CONTRACTOR PERSONNEL: 10 <br />EQUIPMENT ON SITE: Excavator, Drill Rig, Track Loader, 3 OHV's, 4 Pickup Tr <br />3 Equipment Trailers, Fusion Machines, Backhoe, 5yd D <br />MATERIAL RECEIVED: None <br />VISITORS: None <br />6" PIPE DIA. PIPE DIA. PIPE DIA. <br />170' TRENCHED TRENCHED TRENCHED <br />200' PIPE INSTALLED PIPE INSTALLED PIPE INSTALLED <br />VALVE(S) VALVE(S) VALVE(S) <br />CONSTRUCTION ACTIVITIES <br />Continued to install 6" lateral pipe below grade. Total 6" pipe to date: trenched 520', backfilled 490', and <br />installed 500'. The 6" lateral begins @ EW FU08-04, ends @ area of plans note 29. The 900 elbow was <br />omitted due to pipe being able to sweep the angle point. Pipe crew imorted backfill and offhaul spoils <br />throughout day. Until approx. 2:00 P.M. pipe crew had one OHV operating due to Terex OHV broken <br />down. At 2:00 P.M. approx. crew had a third OHV delivered and their broken down OHV repaired. <br />Drill crew worked 7:00 A.M - 11:30 A.M. fusing well pipe casing. No well drilling took place <br />due to not having the required FAA permit. Pipe crew worked from 6:00 A.M. until 7:00 P.M. <br />Two workers stayed until 8:00 P.M. importing backfill for trenches. EW FU06-16 - staked in wrong loc. <br />Scott @ 11:00 A.M prox. asked Jeff to move to design EI. The 6" x 4" HDPE TEE for EW FU08-02 was <br />fused prior to backfill. Note: 6" lateral trench reached depth of 9' @ pipe station 4+90, extra trench depth <br />began @ pipe station 4+00 and was 4'. <br />By <br />Loren Rush <br />Resident Project Representative <br />