Laserfiche WebLink
TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 45 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste July 17, 2006 Monday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, It. breeze (NW), low 70's to mid 100's Mike Strobel <br /> Equipment on site: <br /> 4x637 scrapers, D6 dozer, 815 compactor, water truck, excavator,rock truck, loader,backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Continued-finishing placement of the Operations Layer over 8 oz. geotextile in the southeast portion of <br /> the upper area of FU-06. <br /> 2. Start finish grading of the floor subgrade in FU-06; paddle wheel scraper and blade using GPS. <br /> 3. Started excavation of the lateral drainages to the sump in the lower floor area subgrade of FU-06. <br /> 4. Start trimming soils along the east side of FU-05 liner limit and detail subgrade along the liner limit at <br /> the southwest corner/south slope of the FU-06 floor area. <br /> 5. GSE representative Ruben Altamirano on site to off load geosynthetics arriving o/a tomorrow. <br /> Il. Testing <br /> 1. Monitored activities. <br /> III. Conversations <br /> • None listed. <br /> Prepared By: Reviewed By: <br /> 1 of 1 4/23/03,Rev. 0 <br />