Laserfiche WebLink
TZE TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 71 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste August 18, 2006 Friday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, Itbreeze (NW),high 50's to high 80's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor, 2 water trucks, excavator, rock truck, loader, backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Continued moisture conditioning the surface of the Clay Liner in the floor area. <br /> II. Testing <br /> 1. Collected Coarse Gravel sample GC-2 for conformance testing. <br /> 2. Collected Fine Gravel sample FG-2 for conformance testing. (Granular Drainage material). <br /> 3. Continued/completed soils testing in on-site soils laboratory. <br /> 4. Continued data entry of completed soils tests. <br /> III. Conversations <br /> • With Monte Christie, Vector Engineering, Inc., re: Site visit. Checked computer data entry, <br /> collected gravel samples and geosynthetics inventories to truck load#19. <br /> Prepared By: Reviewed By: . <br /> 1 of 1 4/23/03,Rev.0 <br />