i /-E TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 105 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste October 2, 2006 Monday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, It. breeze(NW), mid 50's to high 70's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor,2 water trucks, excavator, rock truck, loader,backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Gwinn continued placement of the Granular Drainage Material in the sump; filter geotextile was then <br /> deployed over the drainage material followed by placement of the Operations Layer soils. <br /> 2. Continued installation of the perforated LCRS pipes in the northwest area; Coarse Gravel placed for pipe <br /> bedding, followed by the pipe and l' of Coarse Gravel, all wrapped in Cushion Geotextile. <br /> II. Testing <br /> 1. Monitored activities. <br /> 2. Continued data entry. <br /> 3. Site photo album is up to date. <br /> III. Conversations <br /> • None listed. <br /> Prepared By VIReviewed By: <br /> 1 of 1 4/23/03,Rev. 0 <br />