y 7Z7 TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Report Sequence <br /> Forward WMU FU-06 02.1605.07 107 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Stockton Allied Waste October 4, 2006 Wednesday <br /> General Contractor: Liner Contractor: Project Engineer: Reviewed By: <br /> Gwinn Construction n/a Monte Christie <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Simms n/a <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> Native soils Clear, It. breeze (NW),mid 50's to mid 70's Mike Strobel <br /> Equipment on site: <br /> 4x627 scrapers, 2xD6 dozers, 815 compactor, 2 water trucks, excavator, rock truck, loader, backhoe, forklift <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I. Construction <br /> 1. Gwinn completed placement of the Operations Layer soils down the west side of FU-06. The LCRS <br /> gravel, Filter Geotextile and Operations Layer soils were not tied-in to FU-05 in order to isolate the FU-06 <br /> module for Leak Testing by Vector Engineering, Inc. <br /> 2. Gwinn starts removal of the Temporary Berm at the south end of the Northern Portion of FU-06. <br /> 3. The 12 oz. Geotextile Cushion was placed under the primary LCRS riser pipe. <br /> II. Testing <br /> 1. Monitored activities. <br /> 2. Continued data entry: minor corrections to Proctor Data, etc. <br /> III. Conversations <br /> • With Brian Fritzler, Vector Engineering, Inc., Re: Site visit; tour work area, overlook data, discussed <br /> schedule. <br /> Prepared B Reviewed By: <br /> 1 of 1 4/23/03, Rev.0 <br />