Air Sparging Pilot Test Related Activities Report and Remedial Action Work Plan <br />Former Countryside Market, Stockton, California April 30, 2015 <br />6.1 Air Sparge and Soil Vapor Extraction System Engineering Design <br />The engineered AS and SVE system construction design and layout are included as Figures 6A <br />through 6J which will be used for building, safety permitting and equipment procurement. The <br />following sections detail system equipment components, installation, and construction. <br />6.2 Air Sparge Well Installation <br />The proposed AS well network will consist of ten AS wells (including existing injection wells AS-1 <br />and AS-2). Wells will be spaced along east to west transects that extend diagonally across the <br />Site, generally perpendicular to the flow direction of groundwater. Wells are spaced on <br />approximate 15 to 20-foot centers to provide for overlapping and comprehensive coverage, based <br />on the conservatively estimated 15-foot AS zone of influence from the completed feasibility testing. <br />Well locations are placed within the areal extent of the dissolved-phase hydrocarbon plume. The <br />proposed AS well locations are shown on Figure 5A. <br />Prior to drilling, the locations of all proposed AS wells will be cleared by USA, and then cleared to <br />full auger width using a hand auger or post hole digger. All down-hole drilling equipment will be <br />steam-cleaned to prevent cross-contamination from previous sampling events. <br />AS wells will be constructed using 2-inch Schedule 80 PVC blank and screened (0.010-inch slot) <br />casing. The well screen interval for each of the AS wells will be determined in the field based on <br />the depth to the low permeable horizon. SGI anticipates that the AS wells will be screened from <br />approximately 110 to 115 feet bgs with a 5-foot sump, similar to existing wells AS-1 and AS-2 <br />(Figure 5B). The sparge wells will be installed using hollow stem auger or sonic drilling equipment. <br />Annular seals above the screened intervals will consist of bentonite pellets/grout. Surface <br />completion for the wells will consist of a flush-mounted, traffic-rated remediation well vault set in <br />concrete. <br />All soil cuttings, well development groundwater, and decontamination water generated during <br />drilling and well installation will be contained and stored in U.N.-approved, 55-gallon drums for <br />appropriate disposal via a licensed waste contractor. <br />6.2.1 Air Sparge Remediation Piping <br />SGI will install pressure rated air hose, galvanized (above ground) and/or PVC (buried) piping to <br />the proposed AS well locations. Conveyance piping (3/4 to 1-inch) will be buried in trenches and <br />connected to a manifold within the rennediation compound. A dedicated pipe, or "homerun," will <br />extend from the manifold in the compound to each well. Tie-in at the wellhead will consist of a tee- <br />fitting to enable a threaded cap to be installed on the wellhead for future access for cleanout or <br />gauging. <br />6-2 The Source Group, Inc.