Mr. Geoff Rader, RWQCB <br />Work Plan for Offsite Monitoring Well Installation <br />1120 West Hammer Lane, Stockton, CA <br />Page 3 <br />August 28, 2017 <br />Project No. 2129-1140-01 <br />The initial 5 feet of the boring will be advanced with a hand auger and/or posthole digger <br />to reduce the possibility of damaging underground utilities. <br />Soil samples will be collected in 5-foot intervals during the advancement of the well <br />boring using a California-type, split-spoon sampler equipped with three pre-cleaned brass <br />or stainless-steel sleeves. The ends of the bottom-most, intact sleeve from each sample <br />interval will be lined with TeflonTm sheets, capped, and sealed. Each sample will then be <br />labeled, placed in a resealable plastic bag, and stored in an ice-chilled cooler. Strict <br />chain-of-custody procedures will be followed from the time the samples are collected <br />until the time the samples are relinquished to the laboratory. Additional soil recovered <br />during sampling will be screened for volatile organic compounds wing a photoionization <br />detector (PID). Stratus will record PID readings, soil types, and other pertinent geologic <br />data on a borehole log. Stratus will select the number of soil samples for chemical <br />analyses at the time of the investigation, based on the soil types encountered and field <br />findings during this work. Tentatively, Stratus anticipates submitting soil samples <br />collected from approximately 30, 40, and 50 feet bgs for chemical analysis, unless field <br />observations dictate another course of action. <br />Task 2B: Groundwater Monitoring Well Installation <br />S UILIM 1.jj <br />Groundwater monitoring well MW-13 will be constructed using 2-inch diameter P <br />casing and 20 feet of 0.02-inch factory slotted well screen, extending from approximately <br />30 to 50 feet bgs. A filter pack of #3 sand will be placed in the annular space around the <br />well from the bottom of the well screen to approximately 2 feet above the top of the well <br />screen. Approximately three feet of bentonite chips will be placed on top of the filter <br />pack and hydrated with clean water to provide a transition seal for the well. Neat cement <br />will be used to backfill the remaining annular space around the well casing up to surface <br />grade. The actual well construction may be modified in the field based on conditions <br />encountered at the time of the investigation. <br />Task 2C: Well Development and Sampling <br />Newly installed groundwater monitoring well MW-13 will be allowed to stand a <br />minimum of 72 hours before development. This well will be developed by surging with a <br />bailer, followed by groundwater pumping. Development will continue, to the extent <br />practical, until the development water runs clear and pH and conductivity measurements <br />stabilize. Approximately 10 well casing volumes will be removed during development. <br />After well development and stabilization of the water levels, water levels and the quantity <br />of well volumes removed from the well will be recorded. <br />K:\Knowles-Hanuner LaneWork Plans\knowles-hammer-offsite-well-workplan.doc STRATUS