Neat Cement <br /> Materials: a) Potable Water <br /> b) Type I or II Portland Cement <br /> Mixture: 5.2 to 5.8 gallons of water to every 94-pounds of cement <br /> 1.13 Well Sealing <br /> Procedure <br /> 1. A tremie pipe shall be installed in the well to 10 feet above the measured bottom of <br /> the well. <br /> 2. Slurry (as defined in Section 1.12) shall be pumped with a cement pump into the <br /> casing through the tremie pipe to bring the slurry up to a depth of approximately 5- <br /> feet below ground surface. The bottom of the tremie pipe shall remain submerged <br /> in the slurry throughout the sealing process. The seal shall be placed in one <br /> continuous lift. until all the calculated volume of slurry has been pumped. <br /> 3. A hole shall be excavated around the well casing to a depth of 5 feet below the <br /> ground surface and the well casing and existing cement annular seal removed to the <br /> bottom of this excavation. The slurry shall be allowed to spill over the top of the <br /> casing into the excavation to form a mushroom cap. After the sealing material has <br /> cured, the excavation shall be filled to the level of the surrounding grade with clean <br /> imported fill compacted in 1-foot lifts. The top 5 feet of the casing and slurry shall <br /> become the property of the Contractor. <br /> It is estimated that the abandonment of the well structure will require 50 cubic yards of sealing <br /> material. Additional sealing material, if required to complete abandonment of well structure <br /> according to specifications, shall be billed on a per cubic yard basis as verified by the Owner's <br /> representative. <br /> Payment for Item No. 6, "Sealing Material" shall be at the contract lump sum prices as set forth <br /> in the proposal assuming a total required sealing material volume of 50 cubic yards, and shall <br /> include all labor, materials, tools, equipment, and all work necessary for the completion of <br /> these items. <br /> Payment for Item No. 7, "Extra Sealing Material" shall be at the contract unit prices per yard as <br /> set forth in the proposal and shall include all labor, materials, tools, equipment, and all work <br /> necessary for the completion of these items. <br /> 1.14 CAPPING OF PIPING <br /> Any discharge lines (raw water, overboard, sewer laterals) or any other piping originating from <br /> within the well structure shall be exposed to a depth of 2 feet below ground surface, capped <br /> with an appropriate water tight cap, and covered with fill material finished to match <br /> surrounding grade. <br />